City of Tacoma – RFQ – Alder Powerhouse Unit 11 Rebuild Project – PG19-0150F – Due 8/13/2019

City of Tacoma – RFQ – Alder Powerhouse Unit 11 Rebuild Project – PG19-0150F

Due Date: August 13, 2019 11:00 AM

Pre-Proposal Meeting: A pre-proposal meeting will not be held.

Project Scope: The City of Tacoma seeks Statements of Qualifications (SOQs) from qualified firms to provide Design‐Build (DB) Services for the Alder Unit 11 Rebuild Design‐Build Project (Project). The Project will consist of design, manufacturing, procurement, and construction services
for the replacement, repair, or refurbishment of components of one (1) vertical hydroelectric turbine-generator that has reached the end of its original service life. The unit was originally installed in 1947 and is rated 25 MVA.

Estimate: $4,500,000 – $6,000,000

Specification
Register for the Bid Holders List