City of Tacoma – RFI – Switchgear Cubicle Retrofit – PT20-0132F – Due 5/5/2020
City of Tacoma – RFI – Switchgear Cubicle Retrofit – PT20-0132F
Due Date: May 5, 2020 11:00 AM
Project Scope: Tacoma Power/Transmission & Distribution, the City of Tacoma is issuing this Request for Information (RFI) to obtain guidance on options for retrofitting 15 kV class switchgear circuit breaker cubicles. The objective of this effort is to allow for the use of modern rack-in circuit breakers in existing switchgear cubicles.
Estimate: N/A