Project Scope: The work required for this project includes: electrical modifications and installations to the Port’s 4.16kv and 13.8kv crane power
service at Pier 3 and the installation of fiber optic cable for crane communications along Pier 3 and 4. The electrical work includes but is not limited to; removal and re-installation of existing cable, furnish and installation of new cable, splicing, terminating, testing and installation of Port provided Kirk Key interlock system at the Pier 3 substation. Fiber optic work includes but is not limited to; installation of cable, splicing, terminating and testing.
Bid Estimate: Estimated cost range is $310,000 to $350,000, plus Washington State Sales Tax (WSST).