Turner – Request for Sub Bids – Birney Elementary Tacoma – Due 3/19-3/21 2019

Turner – Request for Sub Bids – Birney Elementary Tacoma

Due Dates: March 19, 20, 21, 2019

Project Scope: The new 60,000 square foot one-story Birney Elementary will stand on the west border of the 8.68-acre property, with the main entrance moving from South 76th Street to South Sheridan Avenue. Four classroom wings connect to the learning commons, with the wings organized so classrooms can expand into a flexible shared learning space and to the adjacent courtyards.

Bid Packages: Acoustical Ceilings, Fireproofing, Roof Anchors, Aggregate Piers, Flooring, Appliance and Food Service Equipment, GWB, Metal Stud Framing, Insulation, Rough Carpentry, Athletic Equipment, Haz-Mat Remediation and Building Demolition, Signage, Athletic Flooring, HVAC, Site Work and Utilities, Concrete, Interior Finishes, Specialty Doors, Electrical and Low Voltage, Landscape and Maintenance, Steel and Misc Metals, Fiber Cement Siding and Air Barrier, Masonry, Storefront and Glazing, Finish Carpentry, Paint and Coatings, Tile, Fire Suppression, Plumbing, and Window Treatments.

Outreach Events:
#1 – Birney Elementary Library – 1202 S 76th St, Tacoma, 98408 – 2/25/2019 4:00p-5:30p
#2 – Turner Construction – Inspire Room – 830 4th Ave S Ste 300, Seattle, 98134 8:00a-9:30a
#3 – Tacoma Municipal Building – 733 Market St, Room 16, Tacoma, 98402 10:00a-11:30a

***Update: Click here to join RFPs which will allow you to view more information, download files and receive future messages.

***Update: See Outreach Presentation Here

See Outreach Flyer here